Comcast Center
Completed June 2006
University of Penn - Proton Therapy Building
Completed October 2008
Bucks County Parking Garage
Completed September 2009
The Statue of Liberty
Completed August 1985 |
|
|
|
|
|
Featured Projects |
Comcast Center- 1701 JFK BLVD Philadelphia, PA 19103
Contractor: L.F. Driscoll Company
Date Completed: June 2006
Scope of Work: 34 Caissons - (12) 8' diameter, (12) 6' diameter, (6) 4' diameter, & (4) 3' diameter
University of Pennsylvania - Proton Therapy Building- 800 Spruce Street, Philadelphia, PA 19104
Contractor: L.F. Driscoll Company
Date Completed: October 2008
Scope of Work: 200 Caissons ranging from 3' to 5' in diameter
Philadelphia Art Museum- 26th Street and the Benjamin Franklin Parkway, Philadelphia, PA 19130
Contractor: L.F. Driscoll Company
Date Completed: August 2007
Scope of Work: 44 Caissons – (7) 4' diameter, (27) 4.5' diameter, & (10) 5' diameter
Temple University- 1800 N. Broad Street Philadelphia, PA 19121
Contractor: Hunter Roberts Construction Group
Date Completed: August 2010
Scope of Work: 40 Caissons ranging from 3-3.5' in diameter at 15-55' deep. 39 Mini Piles at 9 5/8" in diameter to an average depth of 45'. Mini piles were drilled in the basement of Pearson Hall with as low as 8' of vertical clearance
Bucks County Parking Garage- Broad Street, Doylestown, PA 18901
Contractor: Lobar Inc.
Date Completed: September 2009
Scope of Work: 160 Caissons - (103) 3' diameter, (4) 3.5' diameter, (12) 4' diameter, (16) 4.5' diameter, (8) 5' diameter, (7) 5.5' diameter, & (10) 6' diameter
Drexel University Dormitory- 213 N. 34th Street Philadelphia, PA
Contractor: Intech Construction Inc.
Date Completed: December 2008
Scope of Work: 24 Caissons at 5' in diameter to depths of 45'
Lancaster Water Plant- City of Lancaster, Bureau of Water, PA
Contractor: Michael F. Ronca & Sons, Inc.
Date Completed: August 2008
Scope of Work: 133 Caissons - (54) 2.5' diameter, (57) 3' diameter, (18) 4' diameter, (4) 4.5' diameter
Northern Liberties Piazza- 2nd & Germantown Ave, Philadelphia, PA
Contractor: Tower Investments, Inc.
Date Completed: April 2008
Scope of Work: Phase 1: 89 Caissons - (46) 3' diameter, (31) 3.5' diameter, (8) 4' diameter, & (4) 4.5' diameter. Phase 2: 21 Caissons – (15) 3' diameter & (6) 4' diameter
Bicycle and Pedestrian Path- Riverside Park, Manhattan, NY
Contractor: Lomma Construction
Date Completed: March 2008
Scope of Work: 62 Holes at 2' x 28' deep for retaining wall. 40 pre-drilled holes for pipe piles at 16" x 25' deep.
Dorney Park - Possessed Roller Coaster- Bethlehem, PA 18020
Contractor: CC Inc, Construction Services
Date Completed: January 2008
Scope of Work: 24 Caissons – (12) 3' x 38' deep, (4) 4' x 38' deep, (4) 6' x 45' deep, (4) 9' x 50' deep
Addition and Alterations to Paterson PS-24- North Haledon, NJ 07508
Contractor: Delric Construction Company
Date Completed: October 2006
Scope of Work: Caissons ranging from 2.5' – 5' in diameter to depths of 35'
The Statue of Liberty- Liberty Island New York, New York
Contractor: National Elevator Company
Date Completed: August 1985
Scope of Work: Cook Drilling Corporation completed the installation of a 36" diameter, 100 foot deep water tight elevator jack hole within this national monument.
|
|